Bellmouth Contractors
Bellmouth Contractors

Bellmouths

Project Summary

The Yorkshire GREEN project, a National Grid initiative, includes enabling works to prepare the ground for the main construction phase. This includes tasks like constructing bellmouths – temporary access points.

These are essentially widened sections of road or track that allow for easier access for large vehicles and equipment to construction sites.

  • Over 10+ completed.
  • Ranging from 100m2 to 300m2 with a total of 190mm deep.
  • 90mm – 32mm
  • 55mm – 20mm
  • 45mm – HRA
  • Fairly complex and tricky to complete. Using working out into the highway.
  • HRA surface course is known to be the trickiest surface course to carry our correctly.

Project Gallery